It is argued that project teams progress through five stages of team development. Which of the following sequences best represents this progression?

A. forming, norming, storming, performing, reforming
B. forming, storming, norming, performing, adjourning
C. forming, storming, norming, performing, reforming
D. forming, performing, reforming, norming, adjourning

  • School Southern Methodist University
  • Course Title BLI 3302
  • Pages 8
  • Ratings 100% (1) 1 out of 1 people found this document helpful

This preview shows page 6 - 8 out of 8 pages.

Question 131 / 1 ptsAll project teams progress uniformly through five stages of team development.TrueCorrect!False

Question 141 / 1 ptsA project manager understands the importance of understanding individual motives, and takes the time toask each team member what he or she personally wants from being involved in the project.Correct!

Get answer to your question and much more

Question 151 / 1 ptsA project manager's referent power is described as persuading others based upon giving them something.

Get answer to your question and much more

Question 161 / 1 ptsWhen a decision needs to be made quickly or requires significant authority it is often useful to delegatethe decision to one or two team members.

Get answer to your question and much more

Question 171 / 1 ptsVirtually all studies have determined that relationship conflict can contribute positively to a project team'ssuccess.TrueCorrect!False

Question 181 / 1 ptsConflict over ideas on how to proceed with a project can lead to more creative approaches.Correct!

Get answer to your question and much more

Question 191 / 1 ptsWhen a project team member is not performing, rewards may not prove as effective as a coerciveapproach that threatens the team member with undesired consequences.

Get answer to your question and much more

FalseQuestion 201 / 1 ptsThe value of engaging a subject matter expert early in a project should be balanced against the potentiallysignificant cost of paying for his or her expertise over a longer period of time.Correct!

Get answer to your question and much more

Question 211 / 1 ptsThe negotiation process involves several steps such as: preparing for negotiation; knowing your walk-away point; and working towards a common goal.Correct!True

Get answer to your question and much more

End of preview. Want to read all 8 pages?

Upload your study docs or become a

Course Hero member to access this document