Chapter 11 Resource Planning11 Material Requirements Planning
11 Master Production Scheduling
Table 11. Big Truck Tacos has developed the following forecast of demand and accepted orders for their holiday tacos as they enter the Taco Festival Season. They enter the planning period with 65 holiday tacos in inventory as shown in Week 0. Week 0 1 2 3 4 5 6 7 8 Forecast 70 80 90 100 120 140 170 220 Customer Orders 80 50 30 10 0 0 0 0 Projected on- hand inventory 65 MPS ATP
Table 11. Mutts Amazing Dogs has developed the following demand forecast for The Pitbull, a spicy concoction graced by pepperjack cheese, serrano, habanero, poblano and jalapeno peppers, onion, and a cilantro- lime aioli. They enter the planning period with 20 hotdogs in inventory as shown in Week 0. A few customers have standing orders for hotdogs and they have booked catering events over the next two months. They buy their hotdogs in packages of ten just like you and me. Week 0 1 2 3 4 5 6 7 8 Forecast 70 80 90 100 120 140 170 220 Customer Orders 80 50 30 10 0 0 0 0 Projected on- hand inventory 20 MPS ATP
Answer: Difficulty: Moderate Keywords: MPS, master production schedule Learning Outcome: Apply the process of materials requirements planning (MRP) AACSB: Analytical Thinking Learning Obj.: Describe a master production schedule (MPS) and compute available-to-promise quantities. 11 MRP Explosion
A) The periodic order quantity (POQ) rule seeks to create inventory remnants. B) If the POQ rule is used, an item's lot size can vary each time an order is placed. C) The lot-for-lot (L4L) rule is a special case of the fixed-order quantity (FOQ) rule. D) All lot-sizing rules seek to minimize inventory levels. Answer: B Difficulty: Moderate Keywords: lot, sizing, POQ, periodic order quantity Learning Outcome: Apply the process of materials requirements planning (MRP) AACSB: Application of Knowledge Learning Obj.: Apply the logic of an MRP explosion to identify production and purchase orders needed for dependent demand items.
What are the quantities of planned order releases for item ABC for the first five weeks (weeks 1, 2, 3, 4, and 5)? A) 30, 0, 60, 0, 145 B) 60, 0, 145, 0, 0 C) 0, 30, 60, 0, 0 D) 30, 0, 60, 145, 0 Answer: B Difficulty: Moderate Keywords: MRP, material requirements planning, planned order release Learning Outcome: Apply the process of materials requirements planning (MRP) AACSB: Analytical Thinking Learning Obj.: Apply the logic of an MRP explosion to identify production and purchase orders needed for dependent demand items.
What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1, 2, 3, 4, 5, and 6)? A) 20, 30, 0, 40, 20, 0 B) 35, 0, 60, 0, 0, 0 C) 5, 30, 0, 40, 20, 0 D) 35, 0, 0, 40, 20, 0 Answer: A Difficulty: Moderate Keywords: MRP, material requirements planning, planned order release Learning Outcome: Apply the process of materials requirements planning (MRP) AACSB: Analytical Thinking Learning Obj.: Apply the logic of an MRP explosion to identify production and purchase orders needed for dependent demand items.
Which one of the statements concerning item LMN is true? A) The scheduled receipt of 80 units in week 3 should be expedited so that it is finished in week 2. B) The planned order release quantity in week 3 is 80 units. C) The planned receipt quantity in week 6 is 30 units. D) The projected on-hand inventory in week 8 is 70 units. Answer: A Difficulty: Challenging Keywords: scheduled receipt, planned order release, projected on-hand inventory Learning Outcome: Apply the process of materials requirements planning (MRP) AACSB: Analytical Thinking Learning Obj.: Apply the logic of an MRP explosion to identify production and purchase orders needed for dependent demand items.
Scenario 11. Sunshine Manufacturing produces three products: X, Y, Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A. End item Z is assembled from one unit of D and one unit of C; D is manufactured from one unit of A; and C is manufactured from one unit of B.
Scenario 11. Which of the following statements are true of dependent demand?Which of the following statements about dependent demand are true? Dependent demand tends to be more intermittent than independent demand. Once forecasts or production schedules are complete, dependent demand is known exactly.
Which of the following are included in materials with dependent demand?Dependent demand items are components of finished goods—such as raw materials, component parts, and subassemblies—for which the amount of inventory needed depends on the level of production of the final product.
Which of the following is an example of dependent demand?Dependent demand, on the other hand, is demand for component parts or subassemblies. For example, this would be the microchips in the computer, the wheels on the bicycle, or the cheese on the pizza.
What is the name given to the list of quantities of components ingredients and materials required to make a product?A bill of materials (BOM) is a comprehensive inventory of the raw materials, assemblies, subassemblies, parts and components, as well as the quantities of each needed to manufacture a product. In a nutshell, it is the complete list of all the items that are required to build a product.
|