What is a network diagram which is used by the PERT and CPM project management techniques?

Precedence Diagram Method (PDM) is a visual representation technique that depicts the activities involved in a project. It is a method of constructing a project schedule network diagram that uses boxes/nodes to represent activities and connects them with arrows that show the dependencies.

Purpose of Precedence Diagram Method (PDM)

The Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) techniques are essentially limited to “finish-start” relationships (i.e., activity B cannot start until activity A is completed). PDM was developed subsequent to the PERT/CPM techniques and its function is to permit a more accurate depiction of relationships among various activities.

How is the Precedence Diagram Method (PDM) Depicted

The Precedence Diagram is depicted by a chart with nodes and their relationships. An arrow connects two nodes to represent an active relationship. It’s also called a nodal diagram or network diagram.

What is a network diagram which is used by the PERT and CPM project management techniques?
Precedence Diagram Method (PDM)

Precedence Diagram Method (PDM) Benefits

There are a lot of benefits that can be obtained by using the PDM. These are:

  • Highlights relationships and dependencies among activities to ensure planning efficiency.
  • Identifies possible missing activities.
  • Helps identify critical activities to ensure better planning.
  • Helps develop the overall project schedule.
  • Good communication tool for project team members.

The Four Precedence Diagram Methods (PDM)

The PDM has four ways of developing the diagram. These methods are:

  • Finish-Start: In this dependency, an activity cannot start before a previous activity has ended. This is the most commonly used dependency.
  • Start-Start: In this dependency, there is a defined relationship between the start of activities.
  • Finish-Finish: In this dependency, there is a defined relationship between the end dates of activities.
  • Start-Finish: In this dependency, there is a defined relationship between the start of one activity and the end date of a successor activity. This dependency is rarely used.

What is a network diagram which is used by the PERT and CPM project management techniques?
Precedence Diagram Method Dependencies

Steps to Developing a Precedence Diagram

  • Step 1: Break your Work Breakdown Structure (WBS) into activity levels.
  • Step 2: List all activities and their sequences in a table.
  • Step 3: Add relationships and dependencies to each activity in the table.
  • Step 4: Draw the diagram.

Precedence Diagram Method (PDM) Dependency Levels

  • Mandatory Dependency: known as hard logic is an integral part of the work. Example: Activity A must be completed before activity B can start.
  • Discretionary Dependency: preferential or soft logic. Example: Dependency is controlled by the project team and can be changed.
  • External Dependency: Comes from outside of the project. Example: Laws and Regulations or waiting for government funding to begin the project.
  • Internal Dependency: involves a precedence relationship between project activities. Example: Can’t start until the previous internal project is completed.

How a Precedence Diagram Method (PDM) Helps Program Managers

Network scheduling techniques provide Program Managers with a powerful tool for scheduling and controlling their programs/projects. In general, they permit the graphic portrayal of project activities and relationships among the activities. This provides the basis for determining the project’s critical path, predicting shortages, and identifying possible reallocation of resources to solve problems.

Through the use of readily available software, network schedules are fairly easy to update and rework, thus providing managers with current program/project status information and control over activities and schedules. [1]

AcqNotes Tutorial

  • Defense System Management College “Scheduling Guide for Program Managers” – Oct 2001
  • DoD “Integrated Master Plan and Integrated Master Schedule Preparation and User Guide” – 21 Oct 2005
  • CDC “Project Scheduling Best Practices/Guide” – 30 Jun 2007
  • GAO 12-120G “Schedule Assessment Guide: Best Practices for Project Schedule” – May 2012

Updated: 9/7/2022

Rank: G1.5

What is network diagram of PERT and CPM?

PERT applies an “Activity-on-Arrow” network diagram, whereas CPM applies an “Activity-on-Node” network diagram. Activity-on-Arrow means the network diagram depicts each milestone event as a node, and shows the activity information on the arrows joining each milestone event.

What is a network diagram which is used by the PERT and CPM project management techniques multiple choice question?

A PERT chart is a network diagram used in the Program Evaluation Review Technique (PERT) to represent a project's timeline. It allows project managers to estimate the duration of projects based on the analysis of task sequences.

What is CPM and PERT in project network analysis?

PERT vs CPM.